- Working in a live school
- Ground clearance and setting out.
- Connection of new drainage system and other services.
- Excavation and installation of new concrete substructure.
- Installation of new soakaway.
- Installation of new temporary road.
- Complex scaffold installation.
- Setup of a crane and hoist to lower units into correct position.
- New electrical installation with data.
- Full internal fit-out with carpets, SMARTboards, painting etc.
- Installation of new air-conditioning system.
- Installation of DDA compliant powered access doors.
- Playground extension and new parking facilities.
- Various local renewals of paved areas.
- Re-turfing to the grassed areas locally.
- Reinstatement of local playground furniture.
- All delivered within the confines of the school’s summer holiday break.
- Complex management as school was occupied with summer clubs.