Davington School New Build

Works    

  • Working in a live school
  • Ground clearance and setting out.
  • Connection of new drainage system and other services.
  • Excavation and installation of new concrete substructure.
  • Installation of new soakaway.
  • Installation of new temporary road.
  • Complex scaffold installation.
  • Setup of a crane and hoist to lower units into correct position.
  • New electrical installation with data.
  • Full internal fit-out with carpets, SMARTboards, painting etc.
  • Installation of new air-conditioning system.
  • Installation of DDA compliant powered access doors.
  • Playground extension and new parking facilities.
  • Various local renewals of paved areas.
  • Re-turfing to the grassed areas locally.
  • Reinstatement of local playground furniture.
  • All delivered within the confines of the school’s summer holiday break.
  • Complex management as school was occupied with summer clubs.

Awards

  • Finalist for a Modern Methods of Construction Awards 2024
  • Finalist for the RICS Awards 2024